Al-Arada Receives the Somali Ambassador, Dscusses Bilateral Relations Houthi Militia Hit Marib with Ballistic Missile Marib Military and Security Committee Convenes, Condemns Houthi Atrocity in Radaa Al-Arada Inaugurates Saudi-Funded Health & Education Projects PLC VP Al-Arada Attends Closing Ceremony of Special Security and Facilities Forces Training PLC VP Discusses with Health Minister Enhancing Health Services in Liberated Yemeni Governorates PLC VP Al-Arada Attends Funeral of Military Leader Gen Hassan bin Jalal in Marib
Head of the Rural Electricity Authority and a member of the High Supervisory Committee for the Gas Electricity Project in Marib Abdullah Hajar confirmed that over 95% of the project of Marib gas station power plant to link the city with power has completed.
Hajar said in a statement that that the total cost of re-operating the gas station was $ 35 million and $ 337,000.
Hagar noted that the company has finished the construction of 65 out of 80 electrical towers, leaving only 15 towers to be completed during the coming period.
He noted that after the completion of the first phase of supplying Marib city with power , the second phase will start to raise the capacity to more than 100 k. in order to provide electricity for all villages and districts of Marib governorate.